Tuesday, 23 June 2015

First Laggan-Tormore gas by September: Petrofac statement

The Shetland gas plant being built for Total's Laggan-Tormore Project will have gas flowing into it by September, according to a trading update by contractors Petrofac.

The company say: "Construction activities on the Laggan-Tormore project are substantially complete; we are now busy with final completion and pre-commissioning-related activities and our focus remains on delivering first gas in Q3 2015; additional completion and pre-commissioning works are expected to lead to incremental pre-tax costs of approximately £30m; deferred tax asset recognised in respect of tax losses on the project of approximately £20m."

Full Petrofac statement here:http://www.petrofac.com/media/news/2015/june/23/trading-update.aspx

Shetland News story, with background, here: http://www.shetnews.co.uk/news/10916-petrofac-hopeful-of-first-gas-by-end-of-summer


Wednesday, 25 March 2015

Total get Government go-ahead for Edradour and Glenlivet

Total has been given official permission by the UK Government to develop the Edradour and Glenlivet gas fields in the North Sea and connect them to its Laggan-Tormore pipeline.

Full story from Shetland News here: http://www.shetnews.co.uk/news/10376-new-gas-fields-to-come-on-stream


Sunday, 15 March 2015

FT story - Total will auction 20 per cent stake in Laggan Tormore

According to a story in The Financial Times, Total is preparing to auction off just a 20 per cent stake in its Laggan-Tormore development, and would continue to operate the field, including the gas plant in Shetland.

Full story here: http://www.ft.com/cms/s/0/9c00e9ec-c982-11e4-b2ef-00144feab7de.html#axzz3UUKHsDap

Saturday, 14 March 2015

Total to sell Laggan-Tormore for £1 billion - Reuters report

French energy giant Total is planing to sell its Laggan-Tormore gas field, according to the news agency Reuters, quoting 'banking sources'. The gas plant associated with the field is still under construction at Sullom Voe in Shetland and is due to be completed by contractors Petrofac by the end of September, several months behind schedule.

Reuters report that Total will seek around £1 billion for their 80 per cent stake in the field. Development costs for Laggan-Tormore are thought to be approximately £3.5 billion.

Total has refused to comment.

Full Reuters story here: http://uk.reuters.com/article/2015/03/11/total-northsea-idUKL5N0WD3V820150311

Petro Global News follow up here: http://petroglobalnews.com/2015/03/report-total-mulling-sale-of-laggan-tormore-field/

Sunday, 8 March 2015

Total gas plant 'completed by end of September' - new accommodation ship arrives, 2000 staff on site

The Laggan-Tormore Total gas plant contract at Sullom Voe will be completed by the end of September, according to a spokesman for Petrofac.

The company now has five floating accommodation units in Shetland - three barges and two liners. The latest, former cruise ship SNAV Toscana, arrived in Lerwick at the weekend. An incoming workforce of 2000 is now involved in the project.

Full story from The Shetland Times here: http://www.shetlandtimes.co.uk/2015/03/07/new-accommodation-ship-arrives

Wednesday, 12 November 2014

Shetland Gas Plant - exclusive pictures

Promote Shetland is in the process of making a series of films about the energy industry in Shetland for Shetland Islands Council and Highlands and Islands Enterprise. Last week saw the team meeting up with Total's Shetland Gas Plant manager Dave Wink and touring the site.

Looking down over the gas plant to Sullom Voe beyond.


Foundations for a fence!

Probably the strongest fence in the UK...


Road to riches. Beneath this track is the Laggan-Tormore gas pipeline.

Dave Wink, Shetland Gas Plant Manager, Total.

Thursday, 3 July 2014

More Total workers mean new liner. Edradour field full speed ahead.Total buy into Glenlivet

TOTAL has announced that a further 1000 welders and pipe fitters will be brought in to finish its £800m gas plant at Sullom Voe, Shetland, bringing the workforce to 2500. Another liner is sailing north to accommodate the extra workers, joining the various floating accommodation units, former cruise ships, crammed hotels  and temporary hostels currently sited in the isles. First gas is now expected to flow by the end of 2014.

When the cruise ship Gemini arrives next week, Lerwick Harbour will have six floating accommodation units moored.

Total has announced too that it will develop the Edradour field, which will feed gas to the new Laggan-Tormore pipeline and the gas plant at Sullom Voe. Total is partnered by the Danish company DONG Exploration and Production, with which it is also involved in the Glenlivet field. Total has just bought a 60 per cent stake in Glenlivet.

Full story here from Shetland News.http://www.shetnews.co.uk/news/8810-final-push-to-complete-gas-plant


Wednesday, 11 June 2014

£500m Shetland gas sweetening plant gets planning permission

BP's £500m gas sweetening plant at the Sullom Voe Oil Terminal in Shetland has received planning permission from Shetland Islands Council.

Also to be used by Total, which is close to completion of its own massive gas plant on an adjoining site, the BP project will take  three years to build, employing 500 workers. 

It is expected to last 25 years and will employ around 33 full-time workers when fully operational.

Full Shetland Times story here: http://www.shetlandtimes.co.uk/2014/06/11/approval-for-550-million-gas-sweetening-plant/

Thursday, 7 November 2013

Picture: Model and modules at Lerwick Harbour.

A traditional 'Shetland Model' boat at Lerwick with processing modules destined for the Laggan-Tormore gas plant at Sullom Voe in the background. The picture was taken as dusk began to fall.


Tuesday, 25 June 2013

Totally cooking on gas!


It's going to be Shetland's biggest hotel, with 100 rooms. And it's guaranteed to be a success.

The Moorfield Hotel in Brae, near the Sullom Voe Oil Terminal, Scatsta Airport and the new Total gas plant, hub of the massive Laggan-Tormore pipeline development, will open in August with all the accommodation booked by Total for 12 months. And for the following six years, 80 per cent of the rooms will also be reserved for the French firm's employees.
Local folk and tourists will be welcome to eat and drink at the 48,000 sq ft Moorfield - and up to 40 jobs will be created, say developers and management company Redefine BDL Ltd.
Shetland is buzzing with hydrocarbon activity at the moment, both on and offshore.
- Laggan-Tormore: On completion the Shetland gas plant will  process up to 500 million standard cubic feet of gas per day, employing 70 people. The entire project is expected to cost around £2.5bn. 
- Viking Energy: Plans for one of the biggest land-based windfarms in Europe are progressing. It is expected to begin exporting green energy in 2018.
- BP: redevelopment of the Schiehallion field west of Shetland and in the North Sea, the Clair Ridge and Clair South-west developments
-Decommissioning - major developments along the Lerwick waterfront by Lerwick Port Authority and Peterson SBS, among others.
-Aegir wave farm project - a joint venture between Pelamis and Vattenfall
And subscribe to this blog for weekly updates on Shetland's energy businesses. We're on Twitter too and there will be daily updates on Shetland energy news there.