A family-owned firm has erected a large wind turbine on a site in Shetland acquired from energy giant SSE.
Shetland Aerogenerators, operators of the 15-year-old Burradale Wind Farm, one of the most productive in the world, has put up a 3MW Enercon machine at Luggie’s Knowe near Lerwick.
The tower, generator and blade sections were lifted into place by a 750-tonne Liebherr crane with a reach of 85m. The crane was transported to Shetland by the German turbine manufacturer specially for the lift.
Commissioning work and grid connection will follow.
With a tip height of 121m, the Enercon E-82 E4 is Shetland’s largest so far. The Viking Energy project has planning approval for slightly larger 3.6MW machines.
Shetland Aerogenerators took over the development from SSE. Commercial funding for the project was arranged with Lombard Finance.
The power from the turbine will be exported through SSE's Active Network Management system, which was introduced as part of the NINES (Northern Isles New Energy Solutions) project. NINES is designed to let more renewable sources feed in to the local electricity grid.
Shetland Aerogenerators managing director Angus Ward said:
“We originally thought the project could only be built out next year but thanks mainly to the goodwill of SSE we've been able to bring everything forward. “The Enercon is a highly sophisticated machine which will continue producing clean electricity even in high wind conditions.”
Director David Thomson added that the civil works, including excavations, construction of the access road and pouring of the concrete base, had been very ably carried out by local firm Garriock Bros while Orkney firm Bryan J Rendall is doing the specialist electrical works.
“It’s very exciting and satisfying to see the project, which we've been working on for the past year, come to fruition and now we can look forward to the commissioning phase.”
Showing posts with label Viking Energy. Show all posts
Showing posts with label Viking Energy. Show all posts
Tuesday, 4 August 2015
Monday, 9 February 2015
Supreme court decision "about building future for grandchildren" says isles energy group
The Supreme Court's rejection of Sustainable Shetland's appeal against the Viking Energy windfarm in Shetland could mark the creation of a whole new industrial sector for the isles, according to a local energy firm.
The Shetland company Energy Isles, which is developing a wind farm project in Unst and Yell, welcomed the decision to let the Viking Energy project proceed.
Reacting to the final judgement issued by the Supreme Court in London, chairman Paul Riddell said Viking would open the door to further renewables projects that would significantly benefit Shetland communities.
“It’s very rare that an island community with a successful but fragile economy gets to create a whole new sector, but that is what Viking and the interconnector will enable Shetland to do,” he said.
“This judgement gives Energy Isles the potential to bring much-needed income and employment to those areas of Shetland like Unst and Yell which are simply not benefiting from the current economic good times.”
He added: “It’s also about looking ahead 20, 30, 40 years and trying to build a future for our children and grandchildren when the world we take for granted today will have changed dramatically.”
Labels:
Isles,
power,
renewables,
Shetland,
Viking Energy,
wind farm
Last legal barrier to Viking Energy windfarm removed by Supreme Court
The UK’s final court of appeal has dismissed an appeal against the Scottish Government's planning consent for the 103-turbine Viking Energy windfarm in Shetland, and declined to refer the case to the European Court of Justice.
Local campaign group Sustainable Shetland's argument that the effect on the population of Whimbrel was rejected.
The estimate of 3.7 annual
collision deaths was regarded as “very small” in the context of 72-108 annual deaths from other causes. The court was "not satisfied" that the estimated impact of the development on whimbrel was
significant, and considered that the potential beneficial effects of the development's 'habitat management plan' could reasonably be
expected to provide "counterbalancing positive benefits". And even if the level of bird deaths remained, the level of impact was outweighed by the benefits of the project, for example in tackling climate change.
Full judgement available on the Supreme Court website here: https://www.supremecourt.uk/news/latest-judgments.html
Viking Energy chairman Alan Bryce said:
“We are delighted the Supreme Court has endorsed the planning consent for Viking wind farm, granted in April 2012. We can now concentrate on developing what would be one of the world’s most productive wind farms, to generate renewable energy and significant income for the Shetland community.
“I would like to thank all who have supported us in reaching this positive outcome. Viking Energy looks forward to making progress during 2015.”
Labels:
barrier removed,
permission,
Shetland,
Supreme Court,
Viking Energy
Friday, 31 October 2014
Japanese consul general checks out Shetland renewables
The Japanese consul general for Scotland and northern England, Hajime Kitaoka, was in Shetland recently to learn about Viking Energy and other wind and tidal power projects on behalf of his government.
Japan is looking to develop wind and marine renewables on a large scale to reduce its reliance on imported fuels and nuclear power, which fell out of favour after the Fukushima power station disaster in 2011.
Mr Kitaoka toured Shetland Aerogenerators’ Burradale Wind Farm and the sites of the proposed Viking Wind Farm before visiting Cullivoe to hear about North Yell Development Council’s wind farm and tidal energy projects, the wind farm proposed by Energy Isles Limited in Unst and Yell and Aquatera’s proposed tidal power bridge across Bluemull Sound. Earlier he called along SIC vice-convener Cecil Smith at the Town Hall.
From left: Angus Ward of Shetland Aerogenerators talks turbines with Mr Kitaoka and Aaron Priest of Viking Energy.
Labels:
Japan,
Shetland,
Shetland Aerogenerators,
Viking Energy
Friday, 16 May 2014
Viking Energy response to Government consultation on island wind power
|
Thursday, 20 February 2014
Imminent appeal hearing on Viking Energy - legal update and Trump implications
A legal update from law firm Bond Dickinson on the Viking Energy planning situation, the recent decision on Donald Trump's appeal against the offshore wind farm near his Mennie golf development, and the looming Court of Session hearing of the Scottish Government's appeal against the Judicial Review on the Viking development.
http://www.lexology.com/library/detail.aspx?g=bd73cd8f-4bcd-445c-a5b3-f34a011c83ff
Labels:
Court of Session,
judicial review,
Mennie,
Trump,
Viking Energy
Tuesday, 15 October 2013
February and March dates set for Viking Energy appeal
Dates have now been set for hearing the Scottish Government's appeal against Lady Clark's Judicial Review of the granting of planning permission for the Viking Energy windfarm. Three judges in the Inner House of the Court of Session will hear the appeal between 25 and 28 February and again from 4 to 7 March 2014.
Full story from Shetland News here: http://www.shetnews.co.uk/news/7481-date-for-viking-wind-farm-appeal-set
Full story from Shetland News here: http://www.shetnews.co.uk/news/7481-date-for-viking-wind-farm-appeal-set
Labels:
judicial review,
Lady Clark,
renewables,
Shetland,
Viking Energy,
wind farm,
wind power
Viking Energy windfarm planning permission: the legal situation
The judicial review of the Scottish government’s granting of planning permission for the Viking Energy windfarm development in Shetland, sought by local environmental protest group Sustainable Shetland, ruled last month that the permission should be withdrawn.
This was due, said Lady Clark in her judgement, to the fact that Schedule 9 in Section 36 of the Electricity Act Act 1989 required companies to obtain an electricity generating licence from Ofgem before applying to get consent for a project over 50MW. Viking Energy did not have this. She was also 'not satisfied' that the Scottish Government had complied with its obligations under the European 'Wild Birds Directive 2009'.
The ruling regarding the need for a generating licence has provoked major concern throughout the renewables industry and the legal profession regarding its possible impact on up to 32 previous permission granted to windfarm developments, none of which had generating licences.
The Scottish Government has appealed Lady Clark’s decision. It is understood - although there is some disagreement on this - that this has the effect of setting the withdrawal of planning permission aside until the appeal process is concluded.
As this is an important issue for the future of renewable energy in Shetland, Power From The North here draws together a number of links to news stories, the full findings from Lady Clark, magazine articles and legal opinions on the decision and its implications.
Energy Live News 8 October 2013: ‘Shetland(s) ruling could deal blow to renewables in Scotland’ http://www.energylivenews.com/ 2013/10/08/shetlands-ruling- could-deal-blow-to-renewables- in-scotland/
Bond Dickinson (leading UK corporate law firm) 10 October 2013: ‘Court of Session Opinion departs from industry practice in Viking Energy decision’http://www.bonddickinson.com/ insight/comment/court-session- opinion-departs-industry- practice-viking-energy- decision
Macroberts (Scottish legal firm) 7 October 2013: ‘Business will proceed as normal until outcome of appeal is known.’ http://www.macroberts.com/ content/content_1998.html
Pinsent Masons (law firm) 26 September 2013: ‘Departure from industry practice’:http://www.out-law. com/en/articles/2013/ september/viking-energy- decision-on-legality-of- section-36-planning-consent-a- departure-from-industry- practice-says-expert/
Shetland News 24 September 2013: ‘Judge rules against Viking windfarm’http://www.shetnews.co.uk/ news/7387-judge-rules-against- viking-wind-farm
Shetland Times 24 September 2013: ‘Sustainable Shetland ‘pleased’ as judge rules on Viking windfarm: http://www.shetlandtimes.co. uk/2013/09/24/sustainable- shetland-pleased-as-judge- rules-on-viking-wind-farm
Ecologist Magazine 11 October 2013: ‘Winds of Change’http://www.theecologist.org/ News/news_analysis/2105601/ the_winds_of_change.html
Guardian, 3 October 2013: "Ministers do not agree that the application was incompetent under schedule 9 of the Electricity Act, nor do they agree that they failed to take proper account of their obligations under the EU wild birds directive in the decision-making process." http://www.theguardian.com/uk- news/2013/oct/03/shetland- windfarm-viking-project- setback
Full opinion by Lady Clark (133 pages): http://www.scotcourts.gov.uk/ opinions/2013CSOH158.html
Tuesday, 17 September 2013
Viking Energy welcomes Government pricing aid for isles electricity
The Government's announcement of a draft minimum price of £115 per megawatt-hour for isles-generated renewable electricity is “a hugely positive step forwards”, according to Shetland windpower developer Viking Energy.
Full story from The Shetland News here.
Full story from The Shetland News here.
Subscribe to:
Posts (Atom)